One of the major things we always knew we wanted to do to the upstairs unit is to put a dormer on the 3rd floor to add a bathroom. A 4 bedroom/1bathroom unit is a little "under bathroomed" in a modern house, and having a 2nd bathroom in the unit would raise rental income as well as be nicer to move up in to if the time ever comes. However nice it was going to be, we thought that this would be a project reserved for a few years off when we were able to save a bit and things had "settled down". Well, exceptional mortgage rates resulted in us refinancing and all of a sudden making this summer the "right" time to upgrade the rental unit!
 |
| All of the 3rd floor rooms are on the right side of the house |
 |
This picture is pre initial renovation (2 years ago), but the only thing that has changed is that we removed the carpet. This view is in the same orientation as the picture of the house above (rooms are on the right, standing just to the left of the ridge line).
|
To give a quick background, our second unit consists of the 2nd and 3rd floor. The 2nd floor has one bedroom, a kitchen, living room, dining room, and a bathroom. The 3rd floor has three bedrooms, one of which has a gable dormer, and the other two which are sort of in the eaves. The bedrooms cheat a few feet across the center of the house to make them bigger (and not as squashed in the eaves), but there was still around 10 feet left between the interior hallway wall and the outside wall. Perfect for a dormer!
We got a few quotes, and eventually ended up increasing the dormer from a ~20 foot "small" extension to a 34 foot long shed dormer which goes
almost the whole length of our house! The picture below shows the final layout of the dormer. What isn't shown is the fact that the stairs are off the picture next to the bathroom and are included in the dormer because the head high in both stairwells didn't meet modern code.
Other than adding a bathroom, you can see that the washer and dryer are also added to the dormer. Previously the washer and dryer were in the basement, and with three of the bedrooms on the 3rd floor, it meant a long walk down twisty stairs in to the dirty (for now) basement. Not the best for anyone. Now they are right across from all of the bedrooms!
Demolition started in August, and started with a bang! The first activity was gutting the area as well as removing the roof. Removing all of the walls on that side of the house really made it start to feel larger!
When gutted, you can see how little of the floor was actually used previously. You can see the painted floorboards; this is the only space that we were able to use before the renovation.
With everything cleared out, the crew started to frame in the space. You can even get an idea of what the dormer is going to look like
After all of this happened in the first week, progress seemed to slow down massively. There were permit inspections and other things that prevented significant progress. That said, after the second week everything was framed in and the roof was on.
Week three was probably one of the most interesting, with the rough plumbing going in along with the rough electrical. In addition, Steve's crew started working on the making the exterior weather tight. Yes, the siding is the wrong color.
After this, the next most exciting thing was getting the blueboard and durarock (cement board) installed. It REALLY started to look like we were headed in the right direction when everything was closed up.
After this we had about two weeks of plasterers, tiling, finish electrical and plumbing, as well as a bunch of finish work. There was also a decent amount of last minute fixing, as I noticed several workmanship errors which I wanted fixed. Once everything was "up to snuff", Caroline and I (with some help from my mom, Caroline's brother, Sam, and his wife, Katie, and Caroline's sister, Christine) painted everything and put on the finishing touches. All in all, I think it came out pretty well!
We took a ton of pictures throughout the process, which can all be seen here (
http://davroline.smugmug.com/Dormer). The galleries are in reverse chronological order and arranged by what work day they were taken on. Start from the beginning to see the whole process!